FCS has the capability to add change orders within AIA billing. This article will demonstrate the steps to complete this process.
Step 1:
- When a change order is necessary simply click into the Production tab and click on the "Change Order" button on the left side of the page.
Step 2:
- The Change Order window will appear and you will click on the "Add Change Order" button indicated by the black arrow below.
Step 3:
- Using the pulldown menus and open fields, complete the Change Order page including as much detail as possible.
- When completed click "Add" to move on.
Step 4:
- Clicking the "Add" button will take you to a second Change Order page which will list all change orders and allow you to make changes.
Step 5:
- Next, you will need to click on the "Contract" tab on the left side of your screen.
- You will see the changes made to the contract in the grey contract box.
- You will also notice the additional cost of the change order at the bottom of the page.
Step 6:
- The next step is to add the change order to your schedule of values.
- Notice below "Skylights" have been added along with the value of the item.
- You will also see the changes made to the total cost of the job at the bottom of the page.
Step 7:
- Lastly, you will manage the percentages of the change order accordingly.
Congratulations! You have successfully added a change order to your project within AIA billing.